PROJECT OVERVIEW
33 London are regenerating this old site that was formerly The Orb Public House, into two new blocks of flats.
The project is going very well.
PROJECT DELIVERY
All groundworks including reduced level excavation, foundations, temporary works, reinforcement, kerbing, access road. All drainage, block and beam, external works and S278 works.
PROJECT OUTCOME
This project is still ongoing. We have completed the access road, poured concrete foundations, installed drainage and part of the S278 works.
- CLIENT: 33 London
- SECTOR: Public & Domestic
- SITE: Formnerly known as The Orb Public House
- DURATION: 14 weeks
- CONTRACT VALUE: £290,000